Since March 31, a convoy of multi-axle trailers has been inching forward on Mumbai's roads each night, accompanied by escort vehicles including a towing vehicle. The trailers, carrying multiple parts of two tunnel boring machines (TBMs), are on their way from the Jawaharlal Nehru Port (JNPT) to Vikhroli and Savali, a distance of about 62 kilometres and 51 kilometres, respectively. The TBMs, weighing 6,000 tonnes in total, are for the 21-km underground tunnel stretch of the Mumbai-Ahmedabad High ...Read More >

Work has now moved to the installation of critical systems inside the tunnel, the NHSRCL said in a statement. "The 21-km tunnel between Bandra Kurla Complex in Mumbai and Shilphata includes a 5-km NATM section between Ghansoli and Shilphata, where excavation has been completed, paving the way for subsequent construction activities," it said. A drainage system is being developed using specialised casting gantries to ensure safe collection and channelization of seepage water, while waterproofing ...Read More >

Mumbai, Apr 2 (PTI) Work on the 21-km underground tunnel of the Mumbai-Ahmedabad bullet train corridor has progressed to advanced stages, with about 5 km of the stretch excavated using the New Austrian Tunnelling Method (NATM), the National High Speed Rail Corporation Limited (NHSRCL) said on Thursday. Work has now moved to the installation of critical systems inside the tunnel, the NHSRCL said in a statement. "The 21-km tunnel between Bandra Kurla Complex (BKC) in Mumbai and Shilphata include ...Read More >

Surat (Gujarat) [India], April 2 (ANI): The Mumbai-Ahmedabad Bullet Train project will be serviced by three Rolling Stock depots located at Sabarmati and Surat in Gujarat and Thane in Maharashtra. Surat Rolling Stock depot, with an area of about 27 Ha, will be equipped with facilities for the commissioning and maintenance of the trains. It will have state-of-the-art equipment for light maintenance of trainsets with inspection bays, washing plant, stabling lines, etc, an official release said. ...Read More >

Surat (Gujarat) [India], April 2 (ANI): The Mumbai-Ahmedabad Bullet Train project will be serviced by three Rolling Stock depots located at Sabarmati and Surat in Gujarat and Thane in Maharashtra. Surat Rolling Stock depot, with an area of about 27 Ha, will be equipped with facilities for the commissioning and maintenance of the trains. It will have state-of-the-art equipment for light maintenance of trainsets with inspection bays, washing plant, stabling lines, etc, an official release said. ...Read More >
Prime Minister Narendra Modi visited Surat to inspect the ongoing construction of the bullet train station. He reviewed the progress of the Mumbai-Ahmedabad High-Speed Rail Corridor. Later, the Prime Minister will visit Dediapada to address a gathering and inaugurate development projects worth over Rs 9,700 crore. He will also offer prayers at a local temple. Prime Minister Narendra Modi on Saturday visited the under-construction bullet train station in Gujarat's Surat to review the progress of ...Read More >

The Transportation Infrastructure business vertical of Larsen & Toubro has won a large order from the National High Speed Rail Corporation (NHSRCL) to construct 156 Route Km (RKM) of high-speed ballastless track (Package T1) for the Mumbai Ahmedabad High Speed Rail (MAHSR) Corridor. According to the company's project classification, the order is valued in the range of Rs 2,500 crore to Rs 5,000 crore. The scope includes design, supply, construction, testing & commissioning of track-works, on De ...Read More >
Ahmedabad: Work on the bullet train project took a major step forward with the completion of eight large circular piers for a bridge being built over the Sabarmati river in the city. The bridge is part of the Ahmedabad-Mumbai bullet train corridor and will be 36m (about 12 storeys) tall and 480m long.The bridge is being constructed next to the existing Ahmedabad-Delhi railway line. In comparison, the bullet train bridge will be significantly taller -- around 118 feet above the river level.Offici ...Read More >
New Delhi: The Supreme Court Friday asked BJP leader Rajiv Babbar to consider closing the defamation case against Congress MP Shashi Tharoor over his statement comparing Prime Minister Narendra Modi to a scorpion. A division bench of justices MM Sundresh and N Kotiswar Singh verbally remarked "let us close all these things. Why get so touchy about all this? This way, administrators and judges come in the same group and have thick skin". The development took place during the resumed hearing of a ...Read More >
Ahmedabad: Work on the bullet train project took a major step forward with the completion of eight large circular piers for a bridge being built over the Sabarmati river in the city. The bridge is part of the Ahmedabad-Mumbai bullet train corridor and will be 36m (about 12 storeys) tall and 480m long.The bridge is being constructed next to the existing Ahmedabad-Delhi railway line. In comparison, the bullet train bridge will be significantly taller -- around 118 feet above the river level.Offici ...Read More >
Mumbai: Vivek Kumar Gupta, an IRSE officer from the 1988 batch, has taken charge as General Manager, Western Railway. Before this appointment, he served as the Managing Director of NHSRCL, overseeing India's inaugural Bullet Train Project implementation.After taking charge, Gupta conducted an inspection at Churchgate and Marine Lines stations and a footplate inspection of the Churchgate - Marine Lines section on Sunday. He also interacted with passengers and staff. He took note of safety, train ...Read More >

New Delhi [India], July 11 (ANI): The Appointments Committee of the Cabinet has approved extension in services of Govind Mohan as Home Secretary, Ministry of Home Affairs, beyond the date of his superannuation upto August 22, 2026. Home Secretary Govind Mohan is a 1989 Batch Sikkim cadre IAS officer. 'The Appointments Committee of the Cabinet has approved extension in services of Shri Govind Mohan, IAS (SK:89) as Home Secretary, Ministry of Home Affairs beyond the date of his superannuation i. ...Read More >

New Delhi [India], July 11 (ANI): The Appointments Committee of the Cabinet has approved extension in services of Govind Mohan as Home Secretary, Ministry of Home Affairs, beyond the date of his superannuation upto August 22, 2026. Home Secretary Govind Mohan is a 1989 Batch Sikkim cadre IAS officer. Also Read | West Bengal Imposes Luggage Limit on Passengers Travelling by App-Bikes, Sets 10 kg Limit, 36 cm Width Cap on Bags. "The Appointments Committee of the Cabinet has approved extension i ...Read More >

Shilphata (Maharashtra) [India] July 11 (ANI): On July 9, the first breakthrough was achieved in the 21 km long tunnel being constructed between Bandra-Kurla Complex (BKC) and Shilphata in Maharashtra, marking the successful completion of a 2.7 km continuous tunnel section. Out of the total 21 km tunnel, 5 km is being constructed using the New Austrian Tunnelling Method (NATM) between Shilphata and Ghansoli, while the remaining 16 km will be built using Tunnel Boring Machines (TBMs). The tunnel ...Read More >

Thane, Jul 5 (PTI) From deep urban shafts to mountain tunnels and marine crossings, the Bullet Train project is progressing fast, with 80 per cent of excavation work completed at the Bandra Kurla Complex (BKC) station in Mumbai, an official release said on Saturday. Of the 21-km-long underground and undersea tunnel between BKC and Shilphata in Thane district, 16 km is being excavated using Tunnel Boring Machines and 5 km with the help of the New Austrian Tunnelling Method, said the National Hig ...Read More >

2 Mumbai Metros, bullet train & BKC: Metro-3 tunnel will be like subways at Churchgate & CSMT, with shops and travelators. FOB will connect bullet train terminal to 2B's IL&FS 2 Mumbai Metros, bullet train & BKC: In what may come as good news for Mumbai's commuters, the Mumbai-Ahmedabad bullet train will be linked to two Metros - Metro-3 or the aqua line through a tunnel at Bandra-Kurla Complex and 2B via a foot overbridge (FOB), according to reports. The integration is a joint effort led by t ...Read More >

Mumbai: Plans are underway to connect India's first underground bullet train station at Bandra Kurla Complex (BKC) with two metro rail lines and other buildings and commercial complexes around it, said officials. There will be an underground tunnel with a travelator connecting the bullet train station to the Kotak-BKC station of the underground metro Line-3 (Cuffe Parade to Array Colony), and a foot over bridge (FOB) linking it to the IL&FS station on the under-construction Metro Line-2B (DN Nag ...Read More >