India's economic engine is revving up, but navigating the global headwinds requires sharp strategy. The rupee's recent volatility against the dollar underscores the complexities facing Indian businesses, impacting everything from import-export trade to domestic inflation. This week alone, we've seen significant shifts in the IT sector, with major players announcing restructuring and a renewed focus on AI-driven solutions. Meanwhile, the burgeoning startup ecosystem continues to attract substantial funding, despite a cautious global investor sentiment. The government's recent policy announcements on infrastructure development and digitalization are poised to further shape the business landscape, creating both opportunities and challenges for entrepreneurs and established corporations alike. Understanding these market dynamics is crucial for success in today's rapidly evolving Indian economy. Stay informed with Abtak.com for the latest insights and analysis on key sectors including finance, manufacturing, and technology – empowering your business decisions in a dynamic market. Explore the complete business news section now to stay ahead of the curve.

35
BusinessJun 27, 2025 07:32 PM

Rail services to Tripura, Mizoram, Manipur, south Assam remain disrupted for 5th day

Guwahati, Jun 27 (PTI) Rail services to Tripura, Mizoram, Manipur and parts of southern Assam remained suspended for the fifth consecutive day on Friday, even as the Northeast Frontier Railway (NFR) claimed steady progress in restoring the affected Lumding-Badarpur hill section. NFR general manager Chetan Kumar Shrivastava visited the site to review the situation and assess the progress, an official statement said. "Northeast Frontier Railway (NFR) is progressing rapidly towards early restoration of the affected location between KM 108/6-8 in the Lumding - Badarpur Hill Section, which was severely impacted by multiple instances of earth slips due to heavy rainfall," it said. Shrivastava, who visited the site to review the ground situation, directed that maximum manpower and machinery be deployed to expedite the restoration process and ensure early resumption of train services. As part of the restoration efforts, around 20,000 cubic metres of earth that came down from the hill slope are being removed for track fitting, with 14,100 cubic metres already completed. From the track area itself, 3,000 cubic metres of earth were targeted for removal, of which 2,850 cubic metres have already been cleared, it added. In addition, a massive 1,27,000 cubic metres of earth have been removed from vulnerable hill slopes. Drainage improvement measures are also underway, including the construction of 600 metres of kutcha drains and the cleaning of 400 metres of existing hillside drains. "Until restoration is completed, it has been decided to cancel/partial cancel certain trains for the safety of passengers. Passengers are requested to stay updated through official railway communication channels for further information regarding train movements and restoration of services," it added. An NFR bulletin had said on June 23 that the train services had to be suspended as tracks were rendered unsafe owing to "improper" road repair work by NHAI in the area. "On account of boulders along with land mass falling over the railway track in the New Haflong-Jatinga Lampur section owing to improper construction work being undertaken by the NHAI for repairing of road, train services over the Lumding-Badarpur hill section had to be suspended from evening hours of today in order to ensure safety of railway passengers," it said. PTI SSG SSG MNB

Comments

Similar News

26
BusinessJun 27, 2025 07:32 AM

India News | NFR Hopeful of Rail Services Resumption on Lumding-Badarpur Route by June 30 | LatestLY

Guwahati (Assam) [India], June 27 (ANI): The Northeast Frontier Railway (NFR) aims to resume train services on the Lumding-Badarpur Hill section from Monday, following disruptions caused by a major landslide. Approximately 100 meters of track were severely damaged due to a slope failure near an adjacent road, triggered by continuous heavy rainfall in the region. Also Read | Rahul Gandhi's Demand for Digital Voter List of 2024 Lok Sabha Elections and Vidhan Sabha Polls Legally Untenable, Say Experts. Kapinjal Kishore Sharma, Chief Public Relations Officer (CPRO) of NFR, stated that a high-le ...Read More >

17
BusinessJun 29, 2025 04:56 PM

Assam rail connectivity

Guwahati: Six days after severe landslides in Assam's Lumding-Badarpur hill section of the Northeast Frontier Railway (NFR) snapped vital rail connectivity, partial train services have resumed to Tripura, Manipur, Mizoram, and southern Assam. Officials reported on Sunday that limited operations are currently underway, with a full return to normalcy anticipated by Monday, June 30, 2025. Ready for a challenge? Click here to take our quiz and show off your knowledge! Notably, the disruptions in rail connectivity, triggered by heavy rainfall, primarily affected the railway section between KM 10 ...Read More >

17
BusinessJun 29, 2025 02:12 PM

Railway link to parts of Northeast partially restored after six days

Guwahati, Jun 29 (PTI) The railway link to Tripura, Manipur, Mizoram and southern Assam was partially restored on Sunday, six days after it was snapped due to landslides in the Lumding-Badarpur hill section of the Northeast Frontier Railway (NFR), officials said. Limited train operations are being allowed for the time being, with normalisation of movement expected by Monday, they said. "The first goods train and first passenger train (Kanchenjunga Express) crossed the landslide-affected location at Jatinga Lampur after restoration," an NFR spokesperson said. An NFR statement on Saturday eve ...Read More >

20
PoliticsJun 27, 2025 07:42 PM

India News | Rail Services to Tripura, Mizoram, Manipur, South Assam Remain Disrupted for 5th Day | LatestLY

Guwahati, Jun 27 (PTI) Rail services to Tripura, Mizoram, Manipur and parts of southern Assam remained suspended for the fifth consecutive day on Friday, even as the Northeast Frontier Railway (NFR) claimed steady progress in restoring the affected Lumding-Badarpur hill section. NFR general manager Chetan Kumar Shrivastava visited the site to review the situation and assess the progress, an official statement said. Also Read | Lohardaga Shocker: Woman Strangulated, Teen Grandson Hacked to Death in Sleep in Jharkhand, Family Feud Suspected. "Northeast Frontier Railway (NFR) is progressing ra ...Read More >

20
BusinessJun 27, 2025 07:48 AM

NFR hopeful of rail services resumption on Lumding-Badarpur route by June 30

Guwahati (Assam) [India], June 27 (ANI): The Northeast Frontier Railway (NFR) aims to resume train services on the Lumding-Badarpur Hill section from Monday, following disruptions caused by a major landslide. Approximately 100 meters of track were severely damaged due to a slope failure near an adjacent road, triggered by continuous heavy rainfall in the region. Kapinjal Kishore Sharma, Chief Public Relations Officer (CPRO) of NFR, stated that a high-level meeting was held on June 24, involving the Chief Secretary of Assam, the General Manager of NFR, and senior officials from the National H ...Read More >